Banner Health Fort Collins
Before BEE was contracted, the 750 ton capacity chilled water plant in this hospital was operating below Banner Health’s progressive energy standards and far below its capabilities. BEE developed and executed a plan to optimize its performance by implementing ClimaCheck chiller monitoring system, the Cap-and-Ramp cooling tower control method, and several more stages of water-side economizer operation. All energy savings stem from control changes – little new equipment was necessary.
|
Service:
Location: Facility Size: BEE's: Energy Savings |
Measurement and Verification
Fort Collins, CO 146,025 ft long Jessica Lorentz $76,000 per year |